What to Include in a Change Order: 8-Point Checklist

5 min read

A change order should include eight things: the original job reference, what's changing, why, the cost, the schedule impact, the new total, terms, and both signatures. Get it signed before you do the extra work.

The 8-Point Checklist

  1. Original job reference — quote number, date, address.
  2. Description of the change — specific, not "misc. extras."
  3. Reason — customer request, hidden condition, code requirement.
  4. Cost — labor and materials for the change.
  5. Schedule impact — added days, if any.
  6. Revised total — original price plus all approved changes.
  7. Terms — when the extra is due.
  8. Both signatures — yours and the customer's.

Start From a Signed Estimate

Change orders only work when the original scope was clear. See how to write a contractor estimate.

Frequently asked questions

What must a change order include?

+

A reference to the original contract, a description of the change, the reason, the added or removed cost, the schedule impact, the revised contract total, any terms, and signatures from both parties.

Does a change order need to be signed?

+

Yes. Get the customer's signature before doing the extra work. A verbal yes is the most common reason contractors go unpaid for extras.

Can a change order reduce the price?

+

Yes. A deductive change order removes scope and lowers the total. It still needs both signatures.