Real-world examples

What a professional contractor quote looks like

Three real jobs — electrical, plumbing, HVAC — broken down line by line. See exactly how to price labour, mark up materials, and present terms your customer will sign.

Electrician

200A residential panel swap

Replace outdated 100A panel with new 200A service, including meter base, grounding, and 24 breaker spaces.

Customer: Mike Thompson — Dallas, TX

Labour

DescriptionQtyRateTotal
Journeyman — install & terminate8 hr$95$760
Apprentice — assist & cleanup8 hr$55$440
Journeyman — permit & inspection2 hr$95$190

Materials

DescriptionQtyRateTotal
200A main breaker panel (40-space)1 ea$485$485
200A meter base, weather-rated1 ea$165$165
Service entrance cable, 2/0 SER25 ft$10$238
Ground rod, copper-clad 8'2 ea$22$44
Breakers, misc 15/20/30A12 ea$18$216
City permit1 ea$185$185
Labour subtotal$1,390
Materials subtotal$1,333
Fuel surcharge$45
Total$2,768

Notes & terms

  • All work performed to NEC 2023 standards by licensed electrician.
  • Power outage window: 4–6 hours, scheduled in advance.
  • Final inspection by city included.
Plumber

Whole-home PEX repipe

Replace failing copper supply lines throughout 3-bed/2-bath single-story home with PEX-A. Includes drywall access cuts (patching by others).

Customer: Sarah Reyes — Dallas, TX

Labour

DescriptionQtyRateTotal
Journeyman — repipe & manifold install16 hr$105$1,680
Apprentice — assist & pressure test16 hr$60$960
Journeyman — fixture reconnect4 hr$105$420

Materials

DescriptionQtyRateTotal
PEX-A tubing, 1/2" + 3/4"250 ft$2$600
PEX manifold, 12-port1 ea$215$215
Fittings & expansion rings1 lot$175$175
Shut-off valves8 ea$28$224
Insulation sleeves1 lot$85$85
Labour subtotal$3,060
Materials subtotal$1,299
Fuel surcharge$35
Total$4,394

Notes & terms

  • Water shut off no longer than 6 hours per day.
  • Pressure-tested at 100 PSI for 1 hour before walls closed.
  • Drywall repair not included — recommend referral on request.
HVAC

3-ton split system replacement

Remove existing 15-year-old AC + furnace, install new 16 SEER2 3-ton split system with new line set, thermostat, and condensate pump.

Customer: Daniel Park — Dallas, TX

Labour

DescriptionQtyRateTotal
Lead Tech — install & startup10 hr$110$1,100
Helper — assist & haul-away10 hr$55$550
Lead Tech — commissioning & customer walkthrough2 hr$110$220

Materials

DescriptionQtyRateTotal
16 SEER2 3-ton condenser1 ea$2,150$2,150
Matching air handler / coil1 ea$1,485$1,485
Line set, 25' insulated1 ea$235$235
Smart thermostat1 ea$165$165
Condensate pump + drain kit1 ea$85$85
Refrigerant + misc supplies1 lot$145$145
Labour subtotal$1,870
Materials subtotal$4,265
Fuel surcharge$40
Total$6,175

Notes & terms

  • 10-year manufacturer parts warranty + 2-year labour warranty.
  • Old equipment haul-away and EPA-compliant refrigerant recovery included.
  • System commissioned and airflow balanced before sign-off.

Build a quote like this in 90 seconds

Free while in beta. No credit card. No login required to start. Built by a licensed electrician for tradesmen.

Build Your Estimate